The Bridge is now Open!!!

The 10th Ave Bridge officially reopened to all traffic on November 16, 2021 after a ribbon cutting celebration.

Informational Project Video

An overview of the rehabilitation work planned for the historic 10th Avenue Bridge over the Mississippi River along with a look at the water main replacement project. A new water main will be installed under the river as part of the project.
IMG_3620.JPG

Project Description

The 10th Avenue Bridge (Bridge 2796) is a critical transportation element of the Minneapolis riverfront area. Currently, it carries approximately 10,000 motor vehicles and hundreds of pedestrians and bicyclists over the Mississippi River each day.

The bridge is listed on the National Register of Historic Places under Criterion “A” (Community Development – Transportation) and Criterion “C” (Engineering Design).  Built in 1929, it has admirably carried traffic over the Mississippi River for nearly 90 years. However, leaking expansion joints and leaking drainage elements have led to deterioration of concrete components. This deterioration is a mixture of freeze thaw damage and corrosion based damage.

The City of Minneapolis, along with the SEH consultant team, are working together to design a rehabilitation project for the bridge that meets several goals, including:

  • Coordinating with multiple stakeholders and agencies

  • Staying within the project budget

  • Construction that results in an attractive bridge with durable details

  • Does not compromise the historic integrity of the bridge

The design work for the rehabilitation project will be completed by the spring of 2019.  Construction will begin in the fall of 2019, with the majority of the construction work completed by late fall 2020.  The final completion date for construction is July 2021.

In conjunction with the bridge rehabilitation work, the City also plans to replace a large-diameter water main which is suspended from the bridge structure. Installed in 1949, the water main has suffered from many of the same deteriorating conditions as the bridge. The main will be removed from beneath the bridge, and a replacement will be installed underneath the Mississippi River by digging two large, deep shafts on either side of the river and using a specialized tunneling machine to install the new water main beneath the river. Construction of the water main began in late spring 2019 and the new main is expected to be in service by winter 2020.